FUEL & CHEMICAL PROCESSES ›› 2020, Vol. 51 ›› Issue (2): 55-57.

Previous Articles     Next Articles

Analysis for energy saving and environmental benefit of standby boiler system during start-up of coking plant

Xu Guiying  Li Yang   

  1. ACRE Coking & Refractory Engineering Consulting Corporation (Dalian),MCC,Dalian 116085,China
  • Online:2020-03-23 Published:2020-03-24

Abstract:

Analysis is made to configuration of standby boiler system during start-up of independent coking plant and to the energy saving and environmental issues.The result shows that natural gas or COG is the first priority to use for main boiler start-up,and COG is the first priority for standby boiler.Boiler with two kinds of parameters shall be taken for preference for volume selection.Low-position deaerator shall enjoy priority for boiler system arrangement.DeNOx and DeSOx systems should be used for treatment of emission from the boiler.

Key words:

CLC Number: