FUEL & CHEMICAL PROCESSES ›› 2020, Vol. 51 ›› Issue (1): 8-10.

Previous Articles     Next Articles

Practice of shutdown for 4.3 m coke oven of Jiugang Coking Plant

Cao Shihai1  Mu Biao1  Cai Mingzhu2   

  1. 1.Coking Plant of Jiugang (Group) Hongxing Iron & Steel Co.,Ltd.,Jiayuguan 735100,China;2.ACRE Coking & Refractory Engineering Consulting Corporation (Dalian),MCC,Dalian 116085,China
  • Online:2020-01-23 Published:2020-02-21

Abstract: Based on actual situation of 4.3 m coke oven in Jiugang Coking Plant and by analysis of the process,the safe shutdown scheme is prepared and implemented.On the precondition of smooth production,safety and environmental protection, the operation procedure is summarized,i.e.to cut off crude gas transferring system and push all the ovens empty.

Key words: