FUEL & CHEMICAL PROCESSES ›› 2018, Vol. 49 ›› Issue (3): 37-38.
Previous Articles Next Articles
Zhang Wenzheng Tian Yonghua Jiang Fu
Online:
Abstract:
Generally double-loop water feeding system is adopted for supply of boiler feed water.The advantages and disadvantages of double-line feed water system and single-line feed water system are compared.Some suggestions are provided to adopt the single-line feed water system.
CLC Number:
TK229.929
Zhang Wenzheng Tian Yonghua Jiang Fu. Optimization of CDQ boiler feed water system[J]. FUEL & CHEMICAL PROCESSES, 2018, 49(3): 37-38.