FUEL & CHEMICAL PROCESSES ›› 2011, Vol. 42 ›› Issue (1): 18-20.
Previous Articles Next Articles
Xu Ruiyang
Online:
Abstract:
The abnormal variation condition of process parameters such as coke discharge temperature, pre-chamber level and power generating capacity were introduced after dismantlement of the bell type distributor for 150t/h CDQ charging device at Jinan Iron & Steel Company. In combination with the production actual condition, the process parameters, mainly including the central and peripheral air distribution proportion, air-coke ratio and pre-chamber level, were rationally adjusted after dismantlement of distributor.
CLC Number:
TQ520.5
Xu Ruiyang. Adjustment of CDQ process parameters after dismantlement of bell type distributor[J]. FUEL & CHEMICAL PROCESSES, 2011, 42(1): 18-20.
0 / / Recommend
Add to citation manager EndNote|Reference Manager|ProCite|BibTeX|RefWorks
URL: https://journal03.magtechjournal.com/Jwk3_rlyhg/EN/
https://journal03.magtechjournal.com/Jwk3_rlyhg/EN/Y2011/V42/I1/18