摘要:

通过干熄焦工程实例,分析了干熄焦锅炉主蒸汽参数、凝汽参数、循环水系统和汽轮机组的效率对干熄焦热力系统投资和发电量的影响。提高干熄焦热力系统的发电量应根据工程特点进行多方案投资和收益比较,从设计阶段开始选择合理的发电方案。

Abstract:

Through CDQ project examples,analysis is made for the impact of CDQ boiler related data,such as main steam parameters,condensation parameters,circulating water efficiency and steam turbine efficiency,to the CDQ thermal system investment and its power generation capacity.For increasing power generation capacity of the CDQ thermal system,comparison should be made in terms of investments and profits to single out an optimum option before the stage of engineering.