燃料与化工 ›› 2018, Vol. 49 ›› Issue (4): 17-19.

• 煤焦技术 • 上一篇    下一篇

干熄焦事故红焦紧急熄灭喷水系统设计优化

张春才  刘闻菲  胡煜  白银石   

  1. 中冶焦耐工程技术有限公司, 大连116085
  • 出版日期:2018-07-14

Optimization on design of hot coke emergency water spraying system in case of CDQ failure

Zhang Chuncai  Liu Wenfei  Hu YuBai Yinshi   

  1. ACRE Coking & Refractory Engineering Consulting Corporation,MCC,Dalian 116085,China
  • Online:2018-07-14

摘要:

分析了干熄焦事故红焦紧急熄灭喷水系统的组成及给水控制阀门选型,对原有管道布置及给水方案进行优化,可避免焦炭温度过高对带式输送机造成的损伤,保证干熄焦系统的安全生产。

Abstract:

Introductions are given for the configuration of hot coke emergency water spraying system and selection of water feeding control valve.Optimization is also done based on the original piping arrangement and water feeding system to protect belt conveyor against damage which may occur due to excessively high temperature of the not well quenched coke so as to ensure safe production for the CDQ system.