REFRACTORIES & LIME ›› 2023, Vol. 48 ›› Issue (4): 34-35.

Previous Articles     Next Articles

Problems in production and commissioning of double chamber kiln

  

  1. (Guangxi Liugang New Material Technology Co.,Ltd.,Liuzhou 545002,China )
  • Online:2023-08-10 Published:2023-08-14

Abstract: This paper briefly describes the problems in the production and commissioning process of double chamber kiln,such as process calculation,frequent leakage of pulverized coal pipe, unstable kiln quality,air leakage of kiln body reversing valve,etc. analyzes the causes,and puts forward improvement measures to solve. After the improvement,the product quality has been greatly improved.

Key words: Double chamber kiln, Commissioning, Product quality, Improvement measures, Activity