An introduction is given to the heating-up process and key points for 80m long tunnel kiln with small cross section of the Refractory Materials Company of Masteel. It is pointed out that preparation work should be done well in early stage and temperature and pressure should be controlled accurately to ensure the smooth progress of the heating-up process.
CLC Number:
TQ174.654
Liu Qing . Heating-up operation method for 80m long tunnel kiln[J]. REFRACTORIES & LIME, 2011, 36(5): 16-18.